105 Avenue Connector and Hawthorne Park Master Plan

Project Background

105 Avenue

The need for the completion of an east west connector north of 104 Avenue was first identified as part for the Whalley-Guildford Town Centre Plan in the early 1980’s. This was to accommodate and support increasing population from the changes in land use densities from single family homes to multifamily dwellings permitted in the plan area. The new east/west road corridor would improve neighbourhood access and connectivity within the growing community and was officially included as part of the City’s 1986 Official Community Plan (OCP). The alignment for the 105 Avenue connector is reflected in the City’s Road Classification (R-91) Map and is provided below.

105 Avenue connector project location

Project Guiding Principles

The 105 Avenue connector project is a comprehensive and complex project. The City’s five project principles guiding the project are:

1. Deliver Critical Collector Road Connection for the Neighbourhood

As there are currently limited east/west corridors between 104 Avenue and 108 Avenue we've identified that a Collector road connection will provide improved:

  • road connectivity
  • access
  • mobility
  • circulation for the neighbourhood
  • as well as help reduce reliance on arterial roads such as 108 Avenue and 104 Avenue for neighbourhood access.

With the anticipated start of construction for Light Rail Transit (LRT) on 104 Avenue in 2018, which was identified in the Regional Mayors' Council 10-Year Investment Plan, changes to access, including: access restrictions along 104 Avenue, will occur. It is important that this Collector road be provided to ensure reliable and efficient access for the community to City Centre, Guildford and the rest of the City’s transportation system.

2. Mitigate Impacts of the Project

The City recognizes that introducing this planned road connection will be a significant change within the community. The City is committed to minimize impacts related to the project by:

  • aquiring land to replace parkland used for the 105 Avenue connector;
  • investing in the park through the Master Plan process.

​Impacts to Hjorth Road Elementary School’s outdoor play field from the Phase II alignment are anticipated. The City has initiated discussions with School District No. 36 regarding the project plans and is committed to implementing mitigation measures and – similar to Hawthorne Rotary Park – evaluating opportunities for improvements to the School’s outdoor play field.

3. Develop a Master Plan for Hawthorne Park to Improve Access to and Use 

While the project will have impacts to the park in the short term, the City is committed to:

  • developing a master plan for Hawthorne Rotary Park including new and improved park amenities and infrastructure, as well as enhanced natural areas;
  • investing in Hawthorne Rotary Park to mitigate project impacts.

4. Provide High Quality Multi-Modal Facilities

The project is committed to provide high quality multi-modal facilities that support broader City initiatives found in the City’s OCP, Sustainability Charter and Transportation Strategic Plan to support alternative modes of transportation consisting of:

  • off-street separated raised bike lanes;
  • concrete sidewalks and/or asphalt pathways to support mobility within the community and accessibility to transit, Hawthorne Rotary Park, and other destinations;
  • street lighting to improve pedestrian, cyclists, and vehicle visibility;
  • safe accessible pedestrian crossings at select intersections; and
  • On-street parking.

Project Timing

Given the large scope of the project, it will be constructed in a multi-phased program. Phase 1 is planned between Whalley Boulevard and 144 Street, with road construction anticipated to commence in early January 2018, and completed by November 2018. A more detailed schedule is outlined below. Subsequent phases between 144 Street and 150 Street are illustrated on the map.

Public Consultation

The City is committed to a full and inclusive public consultation process. We will maintain this early and ongoing consultation process during all applicable aspects of the project plan development. The community will have multiple opportunities to provide input and the City will consider the public input as advice to guide the Project Principles, described above, for inclusion in the project plans. The City will inform the community about the results of the consultation process to ensure a transparent and accountable process. Information regarding the progress of the project, and regular updates will be available on this webpage.

Past and Upcoming Meetings

    Collapse/Expand All
  • Public Consultation Meeting #1 expand
  • Public Consultation Meeting #1

    The City hosted the first of two public consultation meetings for the project on June 7, 2017 at Guildford Park Secondary School. See the project boards presented on June 7.

    The first public meeting was held to:

    • Introduce the 105 Avenue corridor project history, context, and purpose;
    • Engage with and seek input from the public on the 105 Avenue Corridor plans; and  
    • Engage with and seek input from the public on the Hawthorne Rotary Park Master Plan.  

    Information gathered from this meeting will be used to prepare detail designs for the 105 Avenue corridor project.

    Read the report presented to Council.

  • Public Consultation Meeting #2 expand
  • Public Consultation Meeting #2

    The next public consultation meeting will happen fall 2017. Check back here for date and time.  

Project Schedule for 105 Avenue Connector (Phase 1 and Phase 2)

Activity Anticipated Timing
Information Gathering & Conceptual Design April 2017
Public Consultation Meeting #1 June 7, 2017 at Guildford Park Secondary School, 14707 146 Street. See the display boards.
Detailed Design July to August 2017
Public Consultation Meeting #2 Fall 2017
Phase 1 Construction of Roadwork January 2018
Phase 1 Completion of Roadwork December 2018
Phase 2 Construction (Storm sewer installation between 148 Street and 150 Street) Spring 2018
Phase 2 Completion (Storm sewer installation between 148 Street and 150 Street) December 2018
Phase 2 Construction (Roadwork) Anticipated in 2019
Phase 2 Construction (Roadwork) Anticipated by December 2019

As the project progresses, there may be changes to our planned schedule. We encourage you to check here regularly for updates.